Yelverton


This is the largest job I’ve completed to date. Over 8 tons of lead in total. 

Here are some before and after photos.

It was a significant challenge regarding the logical phased work to keep the building dry during an exceptionally wet Autumn. 

The roof had failed due to a combination of oversized bays, inadequate steps between gutter sections, and severe underside corrosion due to a lack of ventilation. 

All of these issues were rectified by altering the timber deck, and introducing ventilation details which included 4 custom made mid-point free standing vents.